AltaGas Utilities: St. Paul Syndicate Well #2 Re-Abandonment on 49th Avenue

July 5 2017
In July 2016, AUI performed a well re-abandonment, which was, unfortunately, unsuccessful.
Moving forward, the re-abandoned well under go a 2 phase process as follows:
  • Phase 1: Service rig on site, work area fenced- 18 days: July 29 to August 15 (Tentative)
  • Phase 2: Rig and fence removed, normal street access and operation- 10 days: August 16-August 26 (Tentative)
Work is not anticipated to exceed 12 hours per day during daylight hours (8 a.m. - 8 p.m.)

There is no threat to public safety from this leak.

Please follow the links for further information.

If you have further questions, please call 780-980-6190 or by email to stpaulwell@agutl.com